Aerial view of LUCID Validation Track
Document
FT-MOS-VT-001
Rev 02 — Final
Plate 00 — Cover
King Abdullah Economic City, Saudi Arabia · May 2026

The Validation
Track.

A published engineering atlas of the Method of Statement for LUCID Motors' automotive surface validation track at KAEC — six precision section details, executed by FloorTech as specialist subcontractor to Citiscape (Landscape Contractor), under the supervision of Ghafari and Al Bawani.

Owner
LUCID Motors KSA
Consultant
Ghafari Associates / Egis
Main Civil Contractor
Al Bawani Contracting Company
Landscape Contractor
Citiscape Company
Validation Track Subcontractor
FloorTech — GEG
Phase
Phase 02 — Civil & Surface Works
Document
FT-MOS-VT-001
Sheet 01 / 06 — Cover
Contract chain
LUCID Motors
Client / Owner
Ghafari / Egis
Consultant
Al Bawani
Main Civil Contractor
Citiscape
Landscape Contractor
FloorTech — GEG
Validation Track Subcontractor
§ 01 — Overview

A published technical atlas.

Each surface element of the validation track corresponds to a precision shop drawing. This microsite presents them as an atlas of plates, with the complete Method of Statement, ITP and HSE plan as the supporting commentary.

Figure 01
1,100
Track footprint
Figure 02
204
20 MPa concrete
Figure 03
165
Aggregate base course
Figure 04
≈ 600LM
Continuous joint
Figure 05
770pcs
Kerbstones
Figure 06
18
ITP control points
Scope of works

Aggregate Base Course, 20 MPa Pavement, Kerb Plinth, Continuous Contraction Joints, Surface Elements (Cobble, Vienna, Wash Board, Twist, Rope, Angle Iron).

Reference standards
  • 03 30 00Cast-in-Place Concrete
  • 31 23 13.13Aggregate Base Course for Pavement
  • 32 13 73Concrete Paving Joint Sealants
  • ACI 117Tolerances for Concrete Construction
  • ASTM C31/C39Concrete Sampling and Compressive Test
  • EN 1340Concrete Kerb Units
§ 02 — Sequence

Eight steps, in order.

The kerb plinth is poured first — its sharp ink-black edge acts as the side form for the Aggregate Base Course. From that single decision, the rest of the sequence resolves cleanly.

Currently viewing
00Subgrade Handover
Main Contractor
SUBGRADE
00

Subgrade Handover

Main Contractor

Subgrade compacted to ≥ 95 % MDD with CBR ≥ 20 %. Joint inspection and IR-01 sign-off.

28 MPa
01

Kerb Plinth Pour

FloorTech

28 MPa plain concrete plinth, 200 mm thick, flush with FGL. No bedding, no haunching. Sharp edge acts as side form for ABC.

ABC 150
02

Aggregate Base Course

FloorTech

150 mm ABC laid against the kerb plinth and compacted to 95 % MDD / CBR ≥ 80 %. Hand compactor mandatory at edges.

20 MPa
03

20 MPa Pavement Slab

FloorTech

180 mm pavement, 20 MPa, slump 75–125 mm, discharge ≤ 32 °C. Local recesses for Wash Board / Twist zones.

04

Curing

FloorTech

Single coat of curing compound. 7-day continuous wet curing. ACI 117 Class C tolerance.

20 mm
05

Continuous Contraction Joint

FloorTech

20 mm wide × ≥ 45 mm deep saw-cut, while green. Sealed after 30-day cure with elastomeric joint sealant.

06

Kerbstone Installation

FloorTech

Blue and Yellow precast kerbstones bedded on the 28 MPa plinth, aligned to centerline.

07

Surface Elements

FloorTech

Cobble, Vienna, Wash Board, Twist, Rope and Angle Iron installed per individual section MoS.

§ 03 — Plates

Six section details, drawn to scale.

Hover any callout to read the engineering note. Click any plate to open the full-screen lightbox with pan and zoom — useful for site review or projecting on screen during coordination meetings.

Plate 01 / 06Scale 1:5 / 1:150

Concrete Pavement

Base slab build-up — kerb plinth, ABC, 20 MPa pavement

The reference build-up for the entire validation track footprint. The 200 mm 28 MPa kerb plinth is poured first to act as a hard edge form for the 150 mm Aggregate Base Course, which is then compacted with hand-held equipment along the edges. The 180 mm 20 MPa pavement slab is poured against the inner kerb face and finished flush with the top of kerb (T.O.K).

Key dimensions
Kerb plinth thickness
200 mm
Pavement thickness
180 mm
ABC thickness
150 mm
Joint width
20 mm
Joint spacing
≤ 2,000 mm
Hold / Witness Points

Hold Point H-01: Subgrade handover from Main Contractor. Hold Point H-02: Kerb plinth setting-out. Witness Point W-01: ABC compaction test (DCP / Sand-Cone).

Detail
Concrete Pavement — Section 1
Drawn by
FloorTech / GEG
Scale
1:5 / 1:150
Plate
01 / 06
Joint
20 mm
28 MPa Kerb Plinth

Plain concrete 28 MPa, no reinforcement, 200 mm thick perimeter curbing. Continuous contraction joint every 2 m, 20 mm wide.

20 MPa Pavement

Slump 75–125 mm, w/cm ≤ 0.55, discharge temp ≤ 32 °C. 7-day continuous wet curing. Single curing-compound coat per approved comments.

Aggregate Base Course

150 mm ABC, min compaction 95 % MDD, min CBR 80 %.

Continuous Contraction Joint

20 mm wide × ≥ 45 mm deep saw-cut. Sealed after 30-day cure with elastomeric sealant on closed-cell PE backer rod.

Compacted Subgrade

Existing soil reworked by Main Contractor. Min 95 % MDD, CBR ≥ 20 %. Handed over under signed IR-01.

Plate 02 / 06Scale 1:5

Rope Section

Cast-in continuous plate for rope eye-bolt anchorage

Test surface that simulates a transverse rope barrier. Per the approved revision, the 101 mm × 6 mm thick galvanized steel plate is cast continuously into both sides of the slab during the pour — eliminating post-installed drilling and ensuring full pull-out capacity. A galvanized eye-bolt with hex nut and washer threads through the plate, securing the rope assembly.

Key dimensions
Cast-in plate
101 W × 6 THK (continuous both sides)
Eye-bolt
Galvanized, hex nut + washer
Plate weld
Field weld to plate
Joint width
20 mm
Hold / Witness Points

Hold Point H-05: Pre-pour inspection of plate position, alignment and tack welds. Witness Point W-04: Pull-out test on first installed eye-bolt set.

Detail
Rope Section — Section 1
Drawn by
FloorTech / GEG
Scale
1:5
Plate
02 / 06
Joint
20 mm
28 MPa Kerb Plinth

Plain concrete 28 MPa, no reinforcement, 200 mm thick perimeter curbing. Continuous contraction joint every 2 m, 20 mm wide.

101 W × 6 THK Plate

Galvanized steel plate cast-in continuous on both sides during the pour. No drilling. Welded to the eye-bolt assembly on site.

Galvanized Eye-Bolt

Threaded through the cast-in plate; receives hex nut + washer + R36.7 rope. Torque to manufacturer spec.

Aggregate Base Course

150 mm ABC, min compaction 95 % MDD, min CBR 80 %.

Compacted Subgrade

Existing soil reworked by Main Contractor. Min 95 % MDD, CBR ≥ 20 %. Handed over under signed IR-01.

Plate 03 / 06Scale 1:5

Vienna Block / Cobblestone

Natural stone surface bedded on 10 mm mortar

Heritage-stone test zones simulating European cobble road textures. The 20 MPa pavement slab is held down by the stone thickness so the finished stone surface aligns precisely with FGL. A 10 mm cement-mortar bed receives each Vienna Block or natural cobblestone, hand-set to a tight running pattern.

Key dimensions
Mortar thickness
10 mm
Stone thickness
Per approved sample (typ. 80 mm)
Joint width
20 mm pavement contraction joint
Hold / Witness Points

Hold Point H-06: Stone first-line approval. Witness Point W-05: Joint widths and surface flatness within ±3 mm under 3 m straight edge.

Detail
Vienna Block / Cobblestone — Section 1
Drawn by
FloorTech / GEG
Scale
1:5
Plate
03 / 06
Joint
20 mm
28 MPa Kerb Plinth

Plain concrete 28 MPa, no reinforcement, 200 mm thick perimeter curbing. Continuous contraction joint every 2 m, 20 mm wide.

Vienna Block / Cobble

Natural stone face flush with FGL. Pattern, color and thickness per approved mock-up. Sand-broom finish to joints.

10 mm Mortar Bed

Cement mortar 1:3, full bed, no voids, struck wet to receive stone.

Aggregate Base Course

150 mm ABC, min compaction 95 % MDD, min CBR 80 %.

Compacted Subgrade

Existing soil reworked by Main Contractor. Min 95 % MDD, CBR ≥ 20 %. Handed over under signed IR-01.

Plate 04 / 06Scale 1:5

Wash Board

SFRC ridged precast panels on 20 mm screed

High-frequency vibration test surface formed by precast Steel Fibre Reinforced Concrete (SFRC) panels with parallel ridges (R25 mm radius). The base slab is recessed locally and a 20 mm cement screed levels the bedding. Panel dimensions per approved revision: 3,048 mm × 608 mm × 104 mm.

Key dimensions
Panel size
3,048 × 608 × 104 mm
Ridge radius
R25 mm
Ridge spacing
76 mm centres
Screed thickness
20 mm
Hold / Witness Points

Hold Point H-07: Panel pre-installation inspection (dimensions, fibre coverage, no surface cracking). Witness Point W-06: Bedding and final level check.

Detail
Wash Board — Section 1
Drawn by
FloorTech / GEG
Scale
1:5
Plate
04 / 06
Joint
20 mm
28 MPa Kerb Plinth

Plain concrete 28 MPa, no reinforcement, 200 mm thick perimeter curbing. Continuous contraction joint every 2 m, 20 mm wide.

SFRC Panel

Precast SFRC panel — 3,048 × 608 × 104 mm. Ridge profile R25 mm @ 76 mm o/c. Steel fibre 30–35 kg/m³.

20 mm Screed

Cement screed, struck level under panel, no voids.

Aggregate Base Course

150 mm ABC, min compaction 95 % MDD, min CBR 80 %.

Compacted Subgrade

Existing soil reworked by Main Contractor. Min 95 % MDD, CBR ≥ 20 %. Handed over under signed IR-01.

Plate 05 / 06Scale 1:5

Angle Iron

Cast-in galvanized angle with staggered strap anchors

Sharp-edged transverse strip test. A 50.8 × 50.8 × 9.52 mm × 2,895.6 mm long galvanized steel angle is cast 25 mm proud of FGL. Long strap anchors 36.7 × 6.35 × 203.2 mm are welded to the angle and staggered at 300 mm centres, fully embedded in the 20 MPa pavement to develop pull-out resistance.

Key dimensions
Angle section
50.8 × 50.8 × 9.52 mm
Angle length
2,895.6 mm
Strap anchor
36.7 × 6.35 × 203.2 mm
Anchor spacing
300 mm staggered
Protrusion above FGL
25 mm
Hold / Witness Points

Hold Point H-08: Angle alignment, level and weld inspection prior to pour. Witness Point W-07: Pull-out test on representative anchor sample.

Detail
Angle Iron — Section 1
Drawn by
FloorTech / GEG
Scale
1:5
Plate
05 / 06
Joint
20 mm
28 MPa Kerb Plinth

Plain concrete 28 MPa, no reinforcement, 200 mm thick perimeter curbing. Continuous contraction joint every 2 m, 20 mm wide.

Galvanized Angle

L 50.8 × 50.8 × 9.52 mm, 2,895.6 mm long. Cast 25 mm above FGL. Welded to strap anchors below.

Strap Anchors

36.7 × 6.35 × 203.2 mm. Welded to angle, staggered at 300 mm centres, embedded in 20 MPa pavement.

Aggregate Base Course

150 mm ABC, min compaction 95 % MDD, min CBR 80 %.

Compacted Subgrade

Existing soil reworked by Main Contractor. Min 95 % MDD, CBR ≥ 20 %. Handed over under signed IR-01.

Plate 06 / 06Scale 1:5

Twist Board

Precast diagonal-twist plates on 20 mm screed

Body-twist axle articulation test. Precast diagonal-twist plates rise 175 mm above FGL (per approved revision, reduced from the original 850 mm) and are bedded on a 20 mm cement screed over the recessed 20 MPa pavement. Used in Gravity / Mid-size Only configurations along the straight section.

Key dimensions
Twist height (above FGL)
175 mm
Twist length
850 mm
Recess depth
160 mm
Screed thickness
20 mm
Hold / Witness Points

Hold Point H-09: Twist plate pre-installation inspection. Witness Point W-08: Final geometry & 3D scan vs approved mock-up.

Detail
Twist Board — Section 1
Drawn by
FloorTech / GEG
Scale
1:5
Plate
06 / 06
Joint
20 mm
28 MPa Kerb Plinth

Plain concrete 28 MPa, no reinforcement, 200 mm thick perimeter curbing. Continuous contraction joint every 2 m, 20 mm wide.

Twist Plate (175 mm)

Precast diagonal-twist plate. Top of element 175 mm above FGL. Approved Gravity / Mid-size only.

20 mm Screed

Cement screed, full bed under plate.

Aggregate Base Course

150 mm ABC, min compaction 95 % MDD, min CBR 80 %.

Compacted Subgrade

Existing soil reworked by Main Contractor. Min 95 % MDD, CBR ≥ 20 %. Handed over under signed IR-01.

§ 04 — ITP

Inspection & Test Plan.

Eighteen control points spanning subgrade handover through final twist-board geometry — with every Hold gate requiring Consultant sign-off before progressing.

Hold
9
Witness
8
Surveillance
1
RefActivityCriteriaType
H-01Subgrade HandoverCompaction ≥ 95 % MDD, CBR ≥ 20 %, levels ±15 mmHold
H-02Kerb Plinth Setting-OutCenterline, top level, alignment ±5 mmHold
W-01ABC Compaction TestSand-cone / DCP at 250 m² gridWitness
H-03Pre-Pour Inspection (20 MPa)Forms, levels, joints, embedded itemsHold
W-02Concrete SamplingSlump, temp, air; cubes per ASTM C31Witness
S-01Curing Compound ApplicationSingle uniform coat, no bare spotsSurveillance
W-03Saw-Cut JointsWidth 20 mm ± 1, depth ≥ 45 mm, straightness ± 3 mmWitness
H-04Kerbstone Setting-OutLine, level, joint widths per shop drawingHold
H-05Rope Plate Pre-PourPlate alignment, weld quality, anchor spacingHold
W-04Eye-Bolt Pull-Out TestAchieves design pull-out loadWitness
H-06Stone First-Line ApprovalPattern, joint width, flatness ± 3 mm / 3 mHold
W-05Vienna / Cobble Final QCSurface flatness, joint sand fillWitness
H-07SFRC Panel Pre-InstallationDimensions, fibre coverage, no cracksHold
W-06SFRC Panel BeddingFinal levels, no voids under panelWitness
H-08Angle Iron Pre-PourAlignment, level, weld inspectionHold
W-07Angle Anchor Pull-OutSample test per batchWitness
H-09Twist Board Pre-InstallGeometry vs approved mock-upHold
W-08Twist Board Final Geometry3D scan vs approved toleranceWitness
§ 05 — HSE

Risk Register.

Hot-weather scheduling, daily toolbox talks and permits-to-work for hot works and lifting operations frame all site activity at KAEC — in line with the KSA Ministry of HR summer working hour regulations.

PPE Standard: hard hats, safety boots, high-visibility vests, safety glasses and gloves — mandatory across all FloorTech work zones.
Hazard

Heavy Plant Operation

Risk

Crushing / collisions

Mitigation

Trained banksmen, reversing alarms, segregated walkways, certified operators.

Hazard

Concrete Pouring

Risk

Chemical burns / dermatitis

Mitigation

Rubber boots, gloves, long sleeves, immediate washing facilities.

Hazard

Manual Handling

Risk

Musculoskeletal injuries

Mitigation

Mechanical lifting aids for precast; team-lift protocols.

Hazard

Hot Weather (KAEC)

Risk

Heat exhaustion / stroke

Mitigation

Heat stress plan, hydration monitoring, work scheduled for cooler hours.

Hazard

Dust Generation

Risk

Respiratory issues

Mitigation

Water spraying on ABC and access roads, dust masks during cutting.

Hazard

Precast Lifting

Risk

Falling units, crush injuries

Mitigation

Certified lifting equipment, exclusion zone, qualified rigger, daily LOLER check.

Hazard

Concrete Pump Operations

Risk

Line burst / pressure release

Mitigation

Daily inspection, certified operator, exclusion zone.

Hazard

Hot Works (Welding)

Risk

Burns, fire, eye injury

Mitigation

Permit-to-work, fire watch, screens, welding helmet, leather gloves.

Hazard

Saw-Cutting

Risk

Cuts, silica dust, noise

Mitigation

Wet cutting only, hearing protection, silica-rated dust mask, daily blade guard inspection.

§ 06 — Drawing

The reference drawing.

The single shop drawing that governs every section in this atlas — kerbstone arrangement plan, six pavement section details, and constructive build-up. Click to open or download the PDF.

Validation Track Subcontractor

FloorTech

A Gulf Elite Group company — specialist subcontractor to Citiscape, the Landscape Contractor of record.

Engaged for the precision concrete pavements, precast surface elements and engineered jointing of the Validation Track — within the wider landscape package executed by Citiscape for LUCID Motors at KAEC.

Owner
LUCID Motors KSA
Consultant
Ghafari Associates / Egis
Main Civil Contractor
Al Bawani Contracting Company
Landscape Contractor
Citiscape Company
Validation Track Subcontractor
FloorTech — Gulf Elite Group
Document
  • ReferenceFT-MOS-VT-001
  • RevisionRev 02 — Final
  • Issue dateMay 2026
  • Phase02
Approval & sign-off
Prepared by
FloorTech (subcontractor)
FloorTech (subcontractor)
Submitted by
Citiscape (landscape contractor)
Citiscape (landscape contractor)
Reviewed by
Al Bawani (main civil contractor)
Al Bawani (main civil contractor)
Approved by
Ghafari / Egis (consultant)
Ghafari / Egis (consultant)
End of document — FT-MOS-VT-001© 2026 FloorTech / Gulf Elite Group — subcontractor to Citiscape · KAEC, KSA